Site Operations · Dammam, KSA
Site Weekly Report
تقرير الموقع الأسبوعي
SWR-{{week_number}} · {{date_range}}
Project
{{project_name}}
Week #
W-{{week_number}} / 14
Date Range
{{date_range}}
Sponsor
{{client_name}}
Project Mgr
Eng. Khalid Al-Mutairi
Report Date
{{date}}
1Executive Summary الملخص التنفيذي
English
  • Cumulative production reached 1,847 m² of cryogenic insulation installed against weekly target of 1,750 m² — 105.5% achievement, schedule recovering from week 3 dip.
  • Zero Lost-Time Injuries this week; TRIR remains at 0.62 well below Aramco contractor benchmark of 1.20. Two near-misses logged with corrective actions closed.
  • NCR-014 (cold-shoe surface finish) closed with supplier replacement lot; 4 open NCRs remaining, all rated minor and within target closure window.
  • Critical path activity — vapor barrier helium leak test — successfully completed on zones A-1 through A-3 with zero leaks detected; project remains on track for handover {{handover_date}}.
العربية
  • بلغ الإنتاج التراكمي 1,847 م² من العزل شديد البرودة المُركَّب مقابل الهدف الأسبوعي 1,750 م² — تحقيق بنسبة 105.5%، مع تعافي الجدول الزمني من تباطؤ الأسبوع الثالث.
  • صفر إصابات بفقد وقت خلال هذا الأسبوع؛ معدل التكرار الإجمالي للحوادث TRIR عند 0.62 وهو أدنى بكثير من مرجعية مقاولي أرامكو 1.20. تم تسجيل حادثتين محتملتين وإغلاق الإجراءات التصحيحية لهما.
  • أُغلق تقرير عدم المطابقة NCR-014 (تشطيب سطح الحذاء البارد) بعد استبدال المورد للدفعة؛ تبقى 4 تقارير مفتوحة، جميعها بدرجة طفيفة وضمن مدة الإغلاق المستهدفة.
  • أُنجز نشاط المسار الحرج — اختبار التسرب بالهيليوم لحاجز البخار — بنجاح على المناطق من A-1 إلى A-3 مع عدم اكتشاف أي تسرب؛ المشروع لا يزال في المسار لتسليم {{handover_date}}.
2Cumulative Progress & Cost التقدم التراكمي والتكلفة
% Planned · المخطط
67.8 %
Baseline schedule
% Achieved · المنجز
66.2 %
Earned value to-date
Cost-to-Date · التكلفة
SAR 1.51M
Budget SAR 2.29M · 66.0%
Schedule Status · حالة الجدول
−1.6 %
SPI 0.976 RECOVERING
3Safety Statistics إحصائيات السلامة
Indicator · المؤشر This Week Cumulative Target Status
Man-Hours Worked · ساعات العمل5,18452,470ON-TRACK
Lost-Time Injuries (LTIs) · إصابات بفقد وقت000GREEN
Total Recordable Incidents (TRIR) · معدل الحوادث0.000.62≤ 1.20GREEN
Near-Miss Reports · بلاغات الحوادث المحتملة217MONITOR
HSE Trainings Conducted · تدريبات السلامة331≥ 2/wkGREEN
Toolbox Talks Delivered · محاضرات يومية7981/dayGREEN
4Production KPIs مؤشرات الإنتاج الرئيسية
1,847
m² This Week
م² هذا الأسبوع
▲ +18.2 % WoW
1,563
m² Last Week
م² الأسبوع السابق
baseline
105.5 %
% to Weekly Target
% من الهدف الأسبوعي
▲ +5.5 % over
66.2 %
% Project Total
% من إجمالي المشروع
17,991 / 27,200 m²
Vinn Al Azl · Site Weekly Report · v1.0 · CONFIDENTIAL Page 1 / 2
Vinn Al Azl
Vinn Al Azl
Site Weekly Report — Continued
SWR-{{week_number}} · Page 2
5Detailed Activities Mon–Sun الأنشطة التفصيلية اليومية
Day · اليوم Key Activities · الأنشطة الرئيسية Joints NCRs Status
MON
الإثنين
PIR layer 1 zones A-3 to A-7; vapor barrier A-1 to A-3; cold-shoe installation 14 units142381ON-TRACK
TUE
الثلاثاء
PIR layer 2 zones A-3 to A-5; SS cladding start zone A-2; 20 cold-shoes168420ON-TRACK
WED
الأربعاء
SS cladding zone A-2 completion; helium leak test prep zones A-1 to A-3155361MINOR ISSUE
THU
الخميس
Helium leak test execution; PIR application B-1, B-2; QC dimensional checks189520ON-TRACK
FRI
الجمعة
Half-day shift — limited cladding work; safety audit by client HSE87210ON-TRACK
SAT
السبت
PIR zones B-3 to B-5; vapor barrier B-1; cold-shoe brackets 18 units196481ON-TRACK
SUN
الأحد
SS cladding zone B-1; final inspection zones A-1 to A-3; ITP closeout210541ON-TRACK
TOTALWeekly cumulative1,1472914
6Material Received (Week) المواد المستلمة هذا الأسبوع
# Material · المادة PO / MTR Ref Qty UoM QC Status
01PIR Foam Boards 45 kg/m³ × 200 mmPO-{{po_number}} / MTR-04181,840Accepted
02SS 304L Cladding 1.0 mm × 1250 mmPO-{{po_number}} / MTR-0421980Accepted
03Vapor Barrier Aluminum-Foil 0.25 mmPO-{{po_number}} / MTR-042584rollsAccepted
04Cold-Shoe Brackets CS-450 SS304PO-{{po_number}} / MTR-043296pcs92 Acc / 4 NCR
05SS Bands 19 mm + Sealant PermabondPO-{{po_number}} / MTR-043842rolls/kitsAccepted
7Issues · Resolutions · Escalations الملاحظات والحلول والتصعيد
Ref Issue · المشكلة Resolution · الحل Owner Status
NCR-014Cold-shoe brackets surface pitting exceeded Ra 6.3 μm — 4 of 24 units lot M-05.Supplier replaced lot under warranty; new MTR-0432 received Thu; 96 units passed QC.QC LeadCLOSED
NCR-015Cladding panel zone A-2 — minor overlap deviation +4 mm beyond ±2 mm spec.Section re-installed Wed; verified within tolerance.ForemanCLOSED
RFI-007Clarification on skirt insulation termination detail at +18 m elevation.Client engineering issued reply Thu; revised shop drawing VAZ-DWG-031 Rev C.PMCLOSED
ESC-002Late delivery of helium leak test gas cylinders — supplier 3 days behind.Escalated to Vinn procurement; alternate supplier Linde engaged, delivered Wed AM.ProcurementMITIGATED
8Weekly Site Photos صور الموقع الأسبوعية
Photo 1
Tank T-301 PIR Coverage
Zone A — Elev +14 m
Photo 2
Cold-Shoe Welding
6G Position
Photo 3
Helium Leak Test
Zone A-1 in Progress
Photo 4
SS 304L Cladding
Zone A-2 Finished
Photo 5
Client HSE Audit
Friday Walk-Down
Photo 6
Material Yard
Lot MTR-0438 Receipt
9Plan Next Week & Emerging Risks خطة الأسبوع القادم والمخاطر
Plan W-{{next_week}} · الخطة
  • Complete PIR application zones B-1 through B-7 (target 1,950 m²).
  • Begin SS 304L cladding zones B-1 to B-3; complete cold-shoe brackets count to 180 units cumulative.
  • Conduct helium leak test on zones A-4 to A-7 and ASTM C518 thermal verification on completed sections.
  • Mobilize second insulation crew for skirt and ring-beam work — 8 additional personnel arriving Sunday.
Emerging Risks · المخاطر
  • Weather: Sandstorm forecast Tue–Wed — cladding work may be suspended 1–2 days. Mitigation: reschedule indoor prefab.
  • Supply: Vapor barrier roll consumption 12% above forecast; additional 30 rolls expedited from Jeddah warehouse.
  • Resource: Welder Bilal Khan annual leave starts W-{{next_week}}+2; replacement Yousef Iqbal confirmed.
  • Regulatory: SASO inspection notice expected W-{{next_week}}+1 — documentation pack ready.
Prepared By · Vinn PM
مُعد من · مدير المشروع
Eng. K. Al-Mutairi{{date}}
Reviewed By · Construction Mgr
مراجَع من · مدير الإنشاء
Name · SignatureDate
Approved By · Client Rep
معتمد من · ممثل العميل
Name · SignatureDate
Vinn Al Azl · Site Weekly Report · v1.0 · CONFIDENTIAL Page 2 / 2