VAA

Vinn Al Azl — Project Quality Plan (PQP) فَنّ العَزْل — خطة الجودة للمشروع

VAA-PQP-{{pqp_no}}
Revision: 1.0
Issued: {{issue_date}}
Per ISO 9001:2015 §8
CONFIDENTIAL · CLIENT COPY · COPY # {{copy_no}}
Project Quality Plan
خطة جودة المشروع
Project-specific implementation of the Vinn Al Azl Quality Management System (ISO 9001:2015), tailored to scope, contractual specifications, and Saudi Aramco engineering standards.
Project
{{project_name}}
RFQ / Contract
{{rfq_ref}}
Client
{{customer}}
Plant / Unit
{{plant_unit}}
Scope
Cryogenic PIR Insulation Supply & Install
Contract Value
SAR {{contract_value}}
Start Date
{{start_date}}
Substantial Completion
{{end_date}}

Approval Matrix · مصفوفة الاعتماد

Preparedإعداد
signature
QA Engineer
Name: ______________
Date: ______________
Checkedمراجعة
signature
QA Manager
Name: ______________
Date: ______________
Approved (VAA)اعتماد فِنّ
signature
Managing Director
Name: ______________
Date: ______________
Accepted (Client)قبول العميل
signature
Client PM / Insp.
Name: ______________
Date: ______________
VAA

Vinn Al Azl — Project Quality Plan (PQP) فَنّ العَزْل — خطة الجودة للمشروع

VAA-PQP-{{pqp_no}}
Page 2 of 4 · Objectives + Organisation
1. Quality Objectives & Project Organisation
١. أهداف الجودة وهيكل المشروع

1.1 · Quality Policy Statement١٫١ · بيان سياسة الجودة

Vinn Al Azl commits to delivering insulation products and field services that conform to client specifications and Saudi Aramco engineering standards (SAES-Q-009, 09-SAMSS-007). Quality is enforced through a documented ISO 9001:2015 QMS, an independent QA function reporting directly to the Managing Director, and unambiguous Hold/Witness/Review authority granted to client inspectors at every critical activity.

تلتزم فَنّ العَزْل بتسليم منتجات عزل وخدمات ميدانية مطابقة لمواصفات العميل ومعايير أرامكو السعودية الهندسية. تُطبّق الجودة عبر نظام موثّق وفق ISO 9001:2015، ووظيفة ضمان جودة مستقلة تتبع المدير العام مباشرةً، وصلاحيات واضحة لمفتّشي العميل في كل نشاط حرج.

1.2 · Project Quality Objectives & KPIs١٫٢ · أهداف ومؤشرات الجودة

Lost Time Injury
0
events on-site
حوادث ضياع وقت
NCR Rate
≤ 1.5
per 1,000 hrs
معدل عدم المطابقة
On-Time Delivery
≥ 98%
vs. milestones
التسليم في الوقت
First-Pass Yield
≥ 95%
inspection pts
قبول من المرة الأولى
Customer Sat.
≥ 4.5
out of 5.0
رضا العميل
Punch Closure
100%
Cat-A within 14d
إغلاق الملاحظات
Audit Findings
0
major NC
نتائج التدقيق
Doc Control
100%
latest rev in use
ضبط الوثائق

1.3 · Project Organisation Chart١٫٣ · الهيكل التنظيمي للمشروع

Project Sponsor (Direct Line)
Managing Director · VAA
المدير العام
Operations
Project Manager
مدير المشروع
Independent Function
QA Manager
مدير ضمان الجودة
Safety
HSE Manager
مدير السلامة
Field Lead
Site Engineer
مهندس الموقع
Quality Control
QC Engineer
مهندس مراقبة الجودة
Inspection
QC Inspector (× 2)
مفتّش جودة
Audit
Internal Auditor
مدقّق داخلي
Execution
Foreman + Insulators
رئيس عمال + فنّيين
Lab
QA Lab Technician
فنّي مختبر
Records
Document Controller
ضابط الوثائق
Materials
Warehouse Lead
مسؤول المستودع

Note: The QA Manager reports directly to the Managing Director and is functionally independent of the Project Manager. This independence ensures quality decisions are not subordinated to schedule pressure.

VAA

Vinn Al Azl — Project Quality Plan (PQP) فَنّ العَزْل — خطة الجودة للمشروع

VAA-PQP-{{pqp_no}}
Page 3 of 4 · QC Flow + Training + Calibration
2. Quality Control Activities
٢. أنشطة مراقبة الجودة

2.1 · Quality Control Activities Flow٢٫١ · تدفّق أنشطة مراقبة الجودة

Reference: VAA-ITP-{{itp_no}} · Inspection & Test Plan

STEP 01
Material Receipt
MTR + COC verified. Visual + density check before storage.
STEP 02
Surface Prep
SSPC-SP3 power tool clean. Dew-point check before adhesive.
STEP 03
PIR Install
Slabs fit-up, banded, staggered joints, sealed with mastic.
STEP 04
Vapor Barrier
DFT ≥ 1.5mm. Holiday/spark test 100% of length.
STEP 05
Cladding
0.8mm aluminum jacket, 50mm laps, SS304 banding.
STEP 06
Pressure Test
1.5 × DP for 30 min. Witnessed by client inspector.
STEP 07
Thermal Soak
IR thermography, no cold spots, ΔT < 8°C from baseline.
STEP 08
Handover
Punch list closed, dossier signed, final certificate issued.

2.2 · Training & Competency Requirements٢٫٢ · متطلبات التدريب والكفاءة

Role · الدور Required Certifications / Training Frequency / Validity Issuing Authority Record / Evidence
QA Managerمدير ضمان الجودةISO 9001 Lead Auditor; SAES-Q-009 awareness; CSWIP/ASNT Level III (optional)Lead Auditor — every 3 yrsIRCA / TÜVVAA-HR-T01
QC Engineerمهندس مراقبة الجودةBSc Mech/Chem Eng; SAEP-1352 familiarisation; min 3 yrs insulationCV review on assignmentSCE-licensedVAA-HR-T02
QC Inspectorمفتّش الجودةDiploma + ASNT VT-II; SAES-Q-009 site induction; 2 yrs field exp.VT — every 5 yrsASNTVAA-HR-T03
NDT Technicianفنّي اختبارات لا إتلافيةASNT Level II VT/PT (as applicable); Pull-off test certifiedEvery 5 yrsASNTVAA-HR-T04
Lab Technicianفنّي مختبرInternal lab competency; ISO/IEC 17025 awarenessAnnual re-assessmentVAA QA MgrVAA-HR-T05
Insulator / Crewفنّي العزلTrade competency test; PPE training; Hot-work permit (where applicable)Re-tested at mobilisationVAA InternalVAA-HR-T06
HSE Officerمسؤول السلامةNEBOSH IGC / OSHA 30; Aramco IH-S permit knowledge3-year refreshNEBOSH / OSHAVAA-HR-T07

2.3 · Calibration Schedule (Project Instruments)٢٫٣ · جدول معايرة الأجهزة

Instrument · الجهاز Reference Calibration Interval Method / Std Provider Record
Heat Flow MeterVAA-HFM-00112 monthsISO 17025 / NISTSAAC labCAL-HFM-{{cal01}}
Universal Test MachineVAA-UTM-00112 monthsASTM E4Instron-MEACAL-UTM-{{cal03}}
Digital Calipers / TapeVAA-MEAS-xx6 monthsISO 13385In-houseCAL-MEAS-{{cal_m}}
Surface ThermometerVAA-TEMP-0016 monthsASTM E230SAAC labCAL-TMP-{{cal_t}}
Dew-Point MeterVAA-DPT-00112 monthsISO 6957Vaisala-MECAL-DPT-{{cal_d}}
Holiday Tester (5 kV)VAA-HLY-00112 monthsNACE SP0188In-houseCAL-HLY-{{cal_h}}
Infrared CameraVAA-IRC-00124 monthsASTM C1153FLIR-MECAL-IRC-{{cal_i}}
Pull-Off TesterVAA-PUL-00112 monthsASTM D4541Defelsko-MECAL-PUL-{{cal_p}}

Note: All calibrations traceable to national standards via SAAC-accredited providers. Out-of-cal instruments are quarantined per VAA-QMS §7.1.5.2.

VAA

Vinn Al Azl — Project Quality Plan (PQP) فَنّ العَزْل — خطة الجودة للمشروع

VAA-PQP-{{pqp_no}}
Page 4 of 4 · NCR + Audit + Risk
3. NCR, Change Control, Audit & Risk
٣. عدم المطابقة، التغييرات، التدقيق، والمخاطر

3.1 · Non-Conformance Report (NCR) Procedure٣٫١ · إجراء عدم المطابقة

Any deviation from specification, drawing, or ITP acceptance criteria shall be raised as a Non-Conformance Report (NCR) on form VAA-F-NCR-01 within 24 hours. NCRs are categorised Cat-A (rework required, work halted), Cat-B (rework required, work may proceed under deviation note), or Cat-C (accepted as-is with technical justification, client concurrence required).

Each NCR follows the 5-step lifecycle: (1) Issue → (2) Root-cause Analysis (5-Why / fishbone) → (3) Disposition (repair / rework / accept-as-is / reject) → (4) Corrective & Preventive Action → (5) Verification & Close-out. Closure requires sign-off by QA Manager and, for Cat-A items, by the client inspector.

3.2 · Change Order Control٣٫٢ · ضبط التغييرات

Any scope or technical change is logged as VAA-F-CHG-01. Approval flow: Originator → QA Mgr → PM → Client. No change is implemented in the field without an approved Change Order and revised drawings.

3.3 · Audit Procedure٣٫٣ · التدقيق الداخلي

Internal audit conducted by an independent auditor every 90 days against this Plan and ISO 9001. Findings logged in VAA-F-AUD-01; major NCs require Corrective Action within 30 days. External (client/Aramco) audits accepted at any time.

3.4 · Document Control٣٫٤ · ضبط الوثائق

All controlled documents (drawings, ITPs, MTRs, NCRs, procedures) are managed in the VAA Document Management System with version control, "controlled copy" stamp, and distribution log. Superseded revisions are marked OBSOLETE and retained per VAA-QMS §7.5.3 (retention: project life + 10 years per Aramco SAEP-122).

3.5 · Top-5 Quality Risk Register٣٫٥ · سجل المخاطر

# Risk · المخاطرة Likeli-hood Impact Score Priority Mitigation Owner
R1 Material rejection at receiptرفض المواد عند الاستلام 2510 MED Pre-shipment MTR verification at factory; documented COC; sealed packaging photos; receiving inspection per ITP §1.0 QA Mgr
R2 Vapor barrier holiday failureفشل اختبار حاجز البخار 248 MED 100% holiday/spark test post-application; trained applicators; daily DFT logs; rework cost absorbed by contractor QC Engineer
R3 Sub-surface moisture during installرطوبة السطح أثناء التركيب 3412 HIGH Pre-shift dew-point measurements; surface temp ≥ 3°C above dew point enforced as Hold point; no work in rain/humidity > 85% Site Engineer
R4 Cold-shoe misalignmentعدم محاذاة الكُتل الباردة 248 MED Survey of pipe rack pre-install; ISO drawing red-lined; tolerance verified at each support as Hold point Site Engineer
R5 NCR escalation / repeat findingsتكرار حالات عدم المطابقة 155 LOW Trend analysis at monthly Quality Review; root-cause analysis for any repeat finding; targeted toolbox talks QA Mgr

Likelihood × Impact (1-5 scale). Score ≥ 12 = High priority (red); 7-11 = Medium (amber); ≤ 6 = Low (green). Reviewed monthly at QA meeting.