Vinn Al Azl — Inspection & Test Plan (ITP)
فَنّ العَزْل — خطة الفحص والاختبار
VAA-ITP-{{itp_no}}
Revision: 1.0
Issued: {{issue_date}}
Per SAES-Q-009 §6
Inspection & Test Plan · Cryogenic PIR Insulation
خطة الفحص والاختبار · عزل البولي يوريثان للظروف الباردة
HHold Point(نقطة توقّف)
WWitness Point(نقطة شهادة)
RReview (post-inspection)(مراجعة لاحقة)
H = work stops · W = notified, may proceed · R = post-doc review
| Activity # |
Activity · النشاط |
Spec Ref |
Method |
Acceptance Criteria |
Frequency |
H/W/R |
VAA Role |
Client Role |
Record / Form |
| 1.0 · Material Receipt & Pre-Installation استلام المواد قبل التركيب |
| 1.1 |
Material receipt inspectionفحص استلام المواد |
SAES-Q-009 §5.2 |
Document + Visual |
MTR + COC + Packing list match PO; no transit damage |
Each delivery |
H |
QC Engineer |
Site Inspector |
VAA-F-101 |
| 1.2 |
Visual inspection of PIR slabs / sectionsالفحص البصري لألواح العزل |
ASTM C390 |
Visual |
No cracks, voids, surface skin damage; uniform color |
100% lots |
W |
QC Inspector |
— |
VAA-F-102 |
| 1.3 |
Density verification (incoming)التحقق من الكثافة |
ASTM D1622 |
Measurement |
40 ± 2 kg/m³ |
1 per batch |
W |
QC Engineer |
Optional |
VAA-F-103 |
| 1.4 |
λ-value batch retestإعادة اختبار الموصلية الحرارية |
ASTM C518 |
Lab Test |
≤ 0.024 W/m·K @ 24°C |
1 per heat |
R |
QA Lab |
Receives MTR |
VAA-MTR-XXXX |
| 1.5 |
Adhesive & sealant shelf-life checkالتحقق من صلاحية المواد اللاصقة |
SAES-Q-009 §5.5 |
Document |
Within mfr. shelf life; storage 5-30°C |
Each lot |
R |
QC Inspector |
— |
VAA-F-104 |
| 2.0 · Surface Preparation & Bond Verification تجهيز السطح والتحقق من الربط |
| 2.1 |
Pipe surface preparationتجهيز سطح الأنبوب |
SSPC-SP3 / 09-SAMSS-007 |
Visual + Test |
Power-tool cleaned; degreased; ≤ 60µm profile |
100% length |
H |
Foreman + QC |
Site Inspector |
VAA-F-201 |
| 2.2 |
Surface moisture & temperatureقياس رطوبة وحرارة السطح |
SAES-Q-009 §6.3 |
Measurement |
Surface temp ≥ 3°C above dew point |
Each shift |
W |
QC Inspector |
— |
VAA-F-202 |
| 2.3 |
Pull-off bond test (adhesion)اختبار الالتصاق |
ASTM D4541 |
Lab Test |
≥ 0.4 MPa pull-off strength |
1 per 50m |
W |
QC Engineer |
Optional |
VAA-F-203 |
| 3.0 · PIR Slab Installation تركيب ألواح البولي يوريثان |
| 3.1 |
PIR slab fit-up & joint clearanceتثبيت الألواح وفتحات الوصلات |
SAES-Q-009 §7.1 |
Visual + Measure |
Joint gap ≤ 2mm; staggered joints ≥ 100mm |
Each section |
W |
Foreman |
Inspector |
VAA-F-301 |
| 3.2 |
Banding / strapping inspectionفحص الأشرطة المعدنية |
09-SAMSS-007 §8 |
Visual |
SS304 bands @ 300mm c/c; flush + clip-locked |
100% |
W |
QC Inspector |
— |
VAA-F-302 |
| 3.3 |
Joint sealing (cryogenic mastic)إغلاق الوصلات |
SAES-Q-009 §7.3 |
Visual |
Continuous bead, no gaps; cure 24h |
100% |
H |
QC Engineer |
Site Inspector |
VAA-F-303 |
Vinn Al Azl — Inspection & Test Plan (ITP)
فَنّ العَزْل — خطة الفحص والاختبار
VAA-ITP-{{itp_no}}
Page 2 of 3 · Vapor Barrier → Commissioning
| Activity # |
Activity · النشاط |
Spec Ref |
Method |
Acceptance Criteria |
Frequency |
H/W/R |
VAA Role |
Client Role |
Record / Form |
| 4.0 · Vapor Barrier & Cladding حاجز البخار والكسوة الخارجية |
| 4.1 |
Vapor barrier applicationتطبيق حاجز البخار |
SAES-Q-009 §8.1 |
Visual + Test |
Continuous; min. DFT 1.5mm; lap ≥ 75mm |
100% |
H |
QC Engineer |
Site Inspector |
VAA-F-401 |
| 4.2 |
Holiday / spark test on vapor barrierاختبار شرارة الفجوات |
NACE SP0188 |
Electrical Test |
No detectable holidays @ 5kV/mm |
100% |
W |
QC Engineer |
Inspector |
VAA-F-402 |
| 4.3 |
Aluminum jacket cladding installationكسوة الألمنيوم الخارجية |
09-SAMSS-007 §10 |
Visual |
0.8mm AlMn1Mg; 50mm lap; banded @ 300mm |
100% |
W |
Foreman + QC |
— |
VAA-F-403 |
| 4.4 |
Weatherproofing of penetrationsإحكام النقاط المعرّضة |
SAES-Q-009 §8.4 |
Visual |
Sealed with grade-A mastic; no exposed insulation |
Each penetration |
H |
QC Engineer |
Site Inspector |
VAA-F-404 |
| 5.0 · Supports & Cold Shoes الدعامات والكُتل الباردة |
| 5.1 |
Cold-shoe positioning & alignmentتمركز ومحاذاة الكُتل الباردة |
SAES-L-310 |
Measurement |
±5mm from drawing; level within 1° |
Each shoe |
H |
Site Engineer |
Site Inspector |
VAA-F-501 |
| 5.2 |
Spring hanger presetضبط المعلّقات الزنبركية |
SAES-L-310 §6.4 |
Measurement |
Cold load setting per ISO drawing |
Each hanger |
W |
Mech. Engineer |
Inspector |
VAA-F-502 |
| 5.3 |
Anti-condensation gap at supportsمنع تكثّف الرطوبة عند الدعامات |
SAES-Q-009 §9.2 |
Visual + Measure |
Continuous vapor seal across support |
Each support |
W |
QC Inspector |
— |
VAA-F-503 |
| 6.0 · Commissioning & Testing التشغيل والاختبار النهائي |
| 6.1 |
System pressure test (post-insulation)اختبار ضغط النظام |
SAES-A-004 |
Test |
1.5 × DP; hold 30 min; no pressure drop |
Each system |
H |
Test Engineer |
Site Inspector |
VAA-F-601 |
| 6.2 |
Thermal-soak commissioningاختبار التشغيل الحراري |
SAES-Q-009 §11 |
Thermography + Log |
Surface temp within ±5°C of design; no cold spots |
Each line |
H |
QC Engineer |
Site Inspector |
VAA-F-602 |
| 6.3 |
Infrared thermography surveyمسح حراري بالأشعة تحت الحمراء |
ASTM C1153 |
Test |
No localized ΔT > 8°C from baseline |
100% length |
W |
QC Engineer |
Optional |
VAA-F-603 |
Vinn Al Azl — Inspection & Test Plan (ITP)
فَنّ العَزْل — خطة الفحص والاختبار
VAA-ITP-{{itp_no}}
Page 3 of 3 · Handover + Approvals
| Activity # |
Activity · النشاط |
Spec Ref |
Method |
Acceptance Criteria |
Frequency |
H/W/R |
VAA Role |
Client Role |
Record / Form |
| 7.0 · Final Walk-Down & Handover المعاينة النهائية والتسليم |
| 7.1 |
As-built drawing reviewمراجعة رسومات حسب التنفيذ |
SAEP-1352 |
Document |
All red-line marks transferred; latest rev approved |
Each ISO |
R |
Project Engineer |
Doc Control |
VAA-F-701 |
| 7.2 |
Final visual walk-downالمعاينة النهائية |
SAES-Q-009 §12 |
Visual |
Cladding flush, no gaps, signage in place |
100% |
H |
QA Manager |
Site Inspector |
VAA-F-702 |
| 7.3 |
Punch list issuance & close-outقائمة الملاحظات وإغلاقها |
SAEP-127 |
Document |
All Cat-A items closed; Cat-B agreed plan |
Each system |
H |
QA Manager |
Site Inspector |
VAA-F-703 |
| 7.4 |
Dossier compilation (MTR + ITP + NCRs)ملف الجودة النهائي |
VAA-QMS §8.5.4 |
Document |
Full traceability; signed by QA Mgr |
1 per scope |
R |
QA Manager |
Doc Control |
VAA-F-704 |
| 7.5 |
Handover certificate & client sign-offشهادة التسليم النهائي |
SAEP-1351 |
Document |
Signed by Vinn QA Mgr + Customer authorised rep |
Each system |
H |
QA Manager |
Site Inspector + PM |
VAA-F-705 |
ITP Approval Matrix
مصفوفة اعتماد الخطة
Prepared By · QA Engineerإعداد · مهندس ضمان الجودة
signature
Name: __________________
Date: __________________
Reviewed By · QA Manager (VAA)مراجعة · مدير ضمان الجودة
signature
Name: __________________
Date: __________________
Approved By · Client Inspectorاعتماد · مفتّش العميل
signature
Name: __________________
Date: __________________
Document Control Note · ملاحظة ضبط المستند: This ITP is a controlled document. Distribution per VAA-QMS §7.5.3. Any modification requires re-approval per the matrix above and shall be issued under a new revision. Aramco-issued comments shall be incorporated via NCR-001 channel.