VAA

Vinn Al Azl — Inspection & Test Plan (ITP) فَنّ العَزْل — خطة الفحص والاختبار

VAA-ITP-{{itp_no}}
Revision: 1.0
Issued: {{issue_date}}
Per SAES-Q-009 §6
Inspection & Test Plan · Cryogenic PIR Insulation
خطة الفحص والاختبار · عزل البولي يوريثان للظروف الباردة
Project
{{project_name}}
RFQ / Contract
{{rfq_ref}}
PO Reference
{{po_ref}}
Plant / Unit
{{plant_unit}}
Scope
Cryogenic Pipe Insulation
Service Temp
−196°C / +110°C
Spec Ref
SAES-Q-009 / 09-SAMSS-007
QMS Reference
VAA-QMS-9001 §8.5
HHold Point(نقطة توقّف)
WWitness Point(نقطة شهادة)
RReview (post-inspection)(مراجعة لاحقة)
H = work stops · W = notified, may proceed · R = post-doc review
Activity # Activity · النشاط Spec Ref Method Acceptance Criteria Frequency H/W/R VAA Role Client Role Record / Form
1.0 · Material Receipt & Pre-Installation استلام المواد قبل التركيب
1.1 Material receipt inspectionفحص استلام المواد SAES-Q-009 §5.2 Document + Visual MTR + COC + Packing list match PO; no transit damage Each delivery H QC Engineer Site Inspector VAA-F-101
1.2 Visual inspection of PIR slabs / sectionsالفحص البصري لألواح العزل ASTM C390 Visual No cracks, voids, surface skin damage; uniform color 100% lots W QC Inspector VAA-F-102
1.3 Density verification (incoming)التحقق من الكثافة ASTM D1622 Measurement 40 ± 2 kg/m³ 1 per batch W QC Engineer Optional VAA-F-103
1.4 λ-value batch retestإعادة اختبار الموصلية الحرارية ASTM C518 Lab Test ≤ 0.024 W/m·K @ 24°C 1 per heat R QA Lab Receives MTR VAA-MTR-XXXX
1.5 Adhesive & sealant shelf-life checkالتحقق من صلاحية المواد اللاصقة SAES-Q-009 §5.5 Document Within mfr. shelf life; storage 5-30°C Each lot R QC Inspector VAA-F-104
2.0 · Surface Preparation & Bond Verification تجهيز السطح والتحقق من الربط
2.1 Pipe surface preparationتجهيز سطح الأنبوب SSPC-SP3 / 09-SAMSS-007 Visual + Test Power-tool cleaned; degreased; ≤ 60µm profile 100% length H Foreman + QC Site Inspector VAA-F-201
2.2 Surface moisture & temperatureقياس رطوبة وحرارة السطح SAES-Q-009 §6.3 Measurement Surface temp ≥ 3°C above dew point Each shift W QC Inspector VAA-F-202
2.3 Pull-off bond test (adhesion)اختبار الالتصاق ASTM D4541 Lab Test ≥ 0.4 MPa pull-off strength 1 per 50m W QC Engineer Optional VAA-F-203
3.0 · PIR Slab Installation تركيب ألواح البولي يوريثان
3.1 PIR slab fit-up & joint clearanceتثبيت الألواح وفتحات الوصلات SAES-Q-009 §7.1 Visual + Measure Joint gap ≤ 2mm; staggered joints ≥ 100mm Each section W Foreman Inspector VAA-F-301
3.2 Banding / strapping inspectionفحص الأشرطة المعدنية 09-SAMSS-007 §8 Visual SS304 bands @ 300mm c/c; flush + clip-locked 100% W QC Inspector VAA-F-302
3.3 Joint sealing (cryogenic mastic)إغلاق الوصلات SAES-Q-009 §7.3 Visual Continuous bead, no gaps; cure 24h 100% H QC Engineer Site Inspector VAA-F-303
VAA

Vinn Al Azl — Inspection & Test Plan (ITP) فَنّ العَزْل — خطة الفحص والاختبار

VAA-ITP-{{itp_no}}
Page 2 of 3 · Vapor Barrier → Commissioning
Activity # Activity · النشاط Spec Ref Method Acceptance Criteria Frequency H/W/R VAA Role Client Role Record / Form
4.0 · Vapor Barrier & Cladding حاجز البخار والكسوة الخارجية
4.1 Vapor barrier applicationتطبيق حاجز البخار SAES-Q-009 §8.1 Visual + Test Continuous; min. DFT 1.5mm; lap ≥ 75mm 100% H QC Engineer Site Inspector VAA-F-401
4.2 Holiday / spark test on vapor barrierاختبار شرارة الفجوات NACE SP0188 Electrical Test No detectable holidays @ 5kV/mm 100% W QC Engineer Inspector VAA-F-402
4.3 Aluminum jacket cladding installationكسوة الألمنيوم الخارجية 09-SAMSS-007 §10 Visual 0.8mm AlMn1Mg; 50mm lap; banded @ 300mm 100% W Foreman + QC VAA-F-403
4.4 Weatherproofing of penetrationsإحكام النقاط المعرّضة SAES-Q-009 §8.4 Visual Sealed with grade-A mastic; no exposed insulation Each penetration H QC Engineer Site Inspector VAA-F-404
5.0 · Supports & Cold Shoes الدعامات والكُتل الباردة
5.1 Cold-shoe positioning & alignmentتمركز ومحاذاة الكُتل الباردة SAES-L-310 Measurement ±5mm from drawing; level within 1° Each shoe H Site Engineer Site Inspector VAA-F-501
5.2 Spring hanger presetضبط المعلّقات الزنبركية SAES-L-310 §6.4 Measurement Cold load setting per ISO drawing Each hanger W Mech. Engineer Inspector VAA-F-502
5.3 Anti-condensation gap at supportsمنع تكثّف الرطوبة عند الدعامات SAES-Q-009 §9.2 Visual + Measure Continuous vapor seal across support Each support W QC Inspector VAA-F-503
6.0 · Commissioning & Testing التشغيل والاختبار النهائي
6.1 System pressure test (post-insulation)اختبار ضغط النظام SAES-A-004 Test 1.5 × DP; hold 30 min; no pressure drop Each system H Test Engineer Site Inspector VAA-F-601
6.2 Thermal-soak commissioningاختبار التشغيل الحراري SAES-Q-009 §11 Thermography + Log Surface temp within ±5°C of design; no cold spots Each line H QC Engineer Site Inspector VAA-F-602
6.3 Infrared thermography surveyمسح حراري بالأشعة تحت الحمراء ASTM C1153 Test No localized ΔT > 8°C from baseline 100% length W QC Engineer Optional VAA-F-603
VAA

Vinn Al Azl — Inspection & Test Plan (ITP) فَنّ العَزْل — خطة الفحص والاختبار

VAA-ITP-{{itp_no}}
Page 3 of 3 · Handover + Approvals
Activity # Activity · النشاط Spec Ref Method Acceptance Criteria Frequency H/W/R VAA Role Client Role Record / Form
7.0 · Final Walk-Down & Handover المعاينة النهائية والتسليم
7.1 As-built drawing reviewمراجعة رسومات حسب التنفيذ SAEP-1352 Document All red-line marks transferred; latest rev approved Each ISO R Project Engineer Doc Control VAA-F-701
7.2 Final visual walk-downالمعاينة النهائية SAES-Q-009 §12 Visual Cladding flush, no gaps, signage in place 100% H QA Manager Site Inspector VAA-F-702
7.3 Punch list issuance & close-outقائمة الملاحظات وإغلاقها SAEP-127 Document All Cat-A items closed; Cat-B agreed plan Each system H QA Manager Site Inspector VAA-F-703
7.4 Dossier compilation (MTR + ITP + NCRs)ملف الجودة النهائي VAA-QMS §8.5.4 Document Full traceability; signed by QA Mgr 1 per scope R QA Manager Doc Control VAA-F-704
7.5 Handover certificate & client sign-offشهادة التسليم النهائي SAEP-1351 Document Signed by Vinn QA Mgr + Customer authorised rep Each system H QA Manager Site Inspector + PM VAA-F-705
ITP Approval Matrix مصفوفة اعتماد الخطة
Prepared By · QA Engineerإعداد · مهندس ضمان الجودة
signature
Name: __________________
Date: __________________
Reviewed By · QA Manager (VAA)مراجعة · مدير ضمان الجودة
signature
Name: __________________
Date: __________________
Approved By · Client Inspectorاعتماد · مفتّش العميل
signature
Name: __________________
Date: __________________
Document Control Note · ملاحظة ضبط المستند: This ITP is a controlled document. Distribution per VAA-QMS §7.5.3. Any modification requires re-approval per the matrix above and shall be issued under a new revision. Aramco-issued comments shall be incorporated via NCR-001 channel.